A 12-by-20-foot room measures 240 square feet whether it faces an open parking lot to the west or sits below a shaded second story. The person in the west-facing room can feel the difference at 5 p.m. A contractor needs more than those two floor dimensions to calculate it. Start with a sketch that shows the windows, the compass direction each one faces, and what lies above, below and on the other side of each wall.

What goes into Manual J
ACCA Manual J is the residential method for estimating how much heat a space gains on a summer design day and loses on a winter one. A ceiling under a vented attic behaves differently from one under a conditioned bedroom. The calculation can account for glazing, shading, insulation and outdoor air entering the home. Have the contractor distinguish measurements from assumptions. A note that reads “attic insulation assumed” gives you something specific to verify before equipment is ordered.
For a one-room system, ask for the figures for that room. For example, the whole-house result might appear at the top of the report, with the office on a separate line farther down. Check the indoor temperature assumed in the calculation, too. A room designed for 75°F has a different target from a room you expect to keep at 69°F all afternoon.
Read the equipment selection beside the load
Imagine that the report for this room shows 5,800 Btu/h of total cooling at its summer design conditions and 7,200 Btu/h of heating at its winter conditions. Those example results belong to one set of assumptions about the room and the weather. If this mini-split will be the only heat source, ask to see its heating output at that winter temperature. On the performance sheet you’ll find that figure in the heating table. Manual S describes how to match equipment performance to the calculated loads.
Before you sign, have the installer mark the room on the floor plan and show you the local outdoor design temperatures used. Ask, “Which window and insulation values did you enter, and where does the selected pair land on its performance table?” Leave with both the room calculation and the model-specific sheet. They make a bid for a different size much easier to evaluate.